Xylem Q 2Rils 485 Signal delivery panel EN 12845 Manuale d'uso

Pagina 42

Advertising
background image

42

9.5.2 Electric pump 1 connections

ELECTRIC PUMP 1

Unit

Terminal board

Terminal

Description

Terminal

Terminal

board

Panel

ELECTRIC PUMP 1

PANEL

See panel

7

Common

2

XC2

KL2

Q-2Rils 485

8

Incorrect phase

sequence

12

9

Pump on demand

14

10

Pump running

16

11

Failure to start

18

Float switch

see float switch

*

Minimum level of

suction tank

2

*

8

Float switch

see float switch

*

Minimum level of

priming tank

2

*

10

* Identify the terminals from the device diagram. In case of alarm, the final contact must be NO.
N.B.:
1) If the priming tank minimum level alarm signal is not used, jumper terminals 2-8 on terminal block XC2 in the Q-2Rils

485 panel.
2) If the priming tank minimum level alarm signal is not used, jumper terminals 2-10 on terminal block XC2 in the Q-
2Rils 485 panel.

9.5.3 Electric pump 2 connections

ELECTRIC PUMP 2

Unit

Terminal board

Terminal

Description

Terminal

Terminal

board

Panel

ELECTRIC PUMP 2

PANEL

See panel

7

Common

2

XC2

KL3

Q-2Rils 485

8

Incorrect phase

sequence

12

9

Pump on demand

14

10

Pump running

16

11

Failure to start

18

Float switch

see float switch

*

Minimum level of

suction tank

2

*

8

Float switch

see float switch

*

Minimum level of

priming tank

2

*

10

* Identify the terminals from the device diagram. In case of alarm, the final contact must be NO.

N.B.:
1) If the priming tank minimum level alarm signal is not used, jumper terminals 2-8 on terminal block XC2 in the Q-2Rils
485 panel.

Advertising